Corral Panel Fabrication Record

A job record for building livestock corral panels, including cut lists, weld counts and field fit checks.

Why keep this record

Corral panels take a beating from animals, weather and tractors. A panel that looks fine on the bench can fail at its first load if the welds are thin, the tubing wall is too light or the gate spacing is wrong for the stock. Use this record to plan each batch, keep the dimensions identical from panel to panel, and log the checks that prove every panel was built the same way. Identical panels let you swap, add and replace sections without surprises.

Worksheet

Panel numberLength and heightRails and tube sizeWeld countStraight and squareCoating applied
Panel 1
Panel 2
Panel 3
Panel 4
Panel 5
Panel 6
Panel 7
Panel 8
Gate frame
Spare or repair

How to complete it

  1. Decide the species and size of animals first. Cattle, sheep and horses need different rail heights and gaps.
  2. Write the pipe or tube size, wall thickness and rail spacing at the top of the sheet. Do not change them mid-batch.
  3. Cut all pieces for the batch from one cut list so lengths match.
  4. Build the first panel on a flat table or fixture, then check every panel against it.
  5. Record every joint welded and any that needed repair.
  6. Look for sharp tabs, burrs or protruding rod ends where animals might rub.

A sample entry

Panel 4, twelve feet long and five feet high with five rails of two inch pipe. Twenty weld joints, all complete. Checked diagonals: 1/8 inch difference, inside the quarter inch limit. One rail end had a sharp burr, ground smooth. Primer applied Tuesday, topcoat Thursday.

Reading the results

When two panels in a batch fail the square check by the same amount, suspect the fixture or the cut list rather than the welder. Compare the failing panels with the first panel, find the pattern, and correct the jig before building more. Rework on a finished panel costs far more time than a ten minute fixture adjustment.

Shop tip

Weld a small steel tag with the panel number and build date on one corner. Years later you can tell which panels are the newest and which came from a different batch, and a repair crew can find the matching spare without measuring everything again.

Stop and get help if

  • A panel is out of square more than the tolerance you set.
  • Any rail or joint shows cracks or undercut.
  • Gaps between rails could trap a leg or head.

Keeping the record

Keep a short note of which panels went to which pen and when. When one panel is bent by a bull or a bumper, you will know the batch it came from and can inspect its neighbors.