Welding Time Estimator
An estimator for the hours a welding job will take, broken into stages with space for actual times.
Why keep this record
Estimating time is the hardest part of pricing, and most people guess too low. Time disappears into layout, fitting, repositioning, grinding, waiting for paint and cleanup. Breaking the job into stages and assigning a time to each makes the guess more realistic. Recording actual times then builds your own data, which becomes more reliable than any chart. Use the sheet for every job, even small ones.
Worksheet
| Stage | Estimated hours | Actual hours | Difference | Notes |
|---|---|---|---|---|
| Planning and drawing | ||||
| Material pickup and handling | ||||
| Cutting and prep | ||||
| Layout and fit-up | ||||
| Tack welding | ||||
| Final welding | ||||
| Grinding and cleanup | ||||
| Painting or coating | ||||
| Assembly and testing | ||||
| Delivery and paperwork |
How to complete it
- Break the project into the stages above and add any special stages, such as machining.
- For each stage, estimate the time using your past records and then add a margin for unknowns.
- Track the actual time by writing start and stop times on the sheet or a shop clock.
- Compare estimated and actual hours at the end and calculate the difference.
- Note what caused large differences, such as poor fit-up or waiting for parts.
- Use the data to adjust future estimates.
A sample entry
Gate: planning 1 hour, pickup 1, cutting 2, fit-up 2, tacking 1, welding 3, grinding 2, painting 1.5, assembly 1, delivery 1. Estimate 15.5 hours. Actual 18, with extra time spent re-fitting a bent rail. Adjusted future gate estimates by 15 percent.
Reading the results
Over time, you can calculate your average hours per foot of weld or per pound of steel for common jobs. Use these rules of thumb for quick quotes, but check them against the sheet for each new type of job.
Shop tip
Estimate times for each stage before you start, then write the actual times at the end of the day, not weeks later. A sheet that is updated each day gives accurate numbers, and a sheet filled in later is guesswork. Keep old sheets, since they become your best resource for quoting.
Common mistakes
- Estimating only the arc time and forgetting fit-up and finishing.
- Not recording actual time, so the next estimate is no better.
- Failing to include travel and shopping.
Stop and get help if
- Your estimate is very different from your history for similar jobs.
- The project involves unfamiliar techniques.
- A deadline depends on the estimate.
Keeping the record
Do not forget non-welding time, which is often more than half of a job. Include trips to buy parts, discussions with the customer and clean up. Ask someone else to review the estimate, since a second opinion often finds a missing stage.